Monday, 29 October 2012

PROGRESS REPORT AKU



To: Sir Azuki Bin Abdul Salam
From: Ahmad Fadhil Bin Mohamed (51210111019)
Date: November 13, 2012
Subject: Progress Report (from July 30 to November 16, 2012): Development Of Solar Power Tracker For  Water Pumping System

Introduction
The purpose of this project is to research about solar power tracker for water pumping system. This project mainly to be used in irrigation such as agriculture.  The project is to easy transfer water efficiently and reliably from sources such as spring, river, tanks and dams. For farmers with a creek running through their properties, using a solar powered water pumping solution means less fouling of waterways and far less erosion of banks.  This progress report discusses the progress I have made from July 30 to November 16.

Work Completed from July 30 to November 16
During this period, I finish do the proposal report, presentation and three chapters from the final report which discussed the Solar Power Tracker for Water Pumping System that will keep the solar panel aligned with the sun and the output of the solar power is used to generate electricity to pump water operations can be done. During the process to finish my report the main task that I learn from this project is how to make the solar panel always follow the sun. The LDR sensor is the important equipment that must have to track the sun. Not forget the servo motor also important to move the solar panel aligned with the sun and most important things is electric water valve can pump water well. I do a lot of research from internet and also some books regarding this project and then compare with my own knowledge. I also have begun working on the program and the controller that I want to use. After do research what type of programming and controller used for this project and I decided to choose controller PIC16f877a and C Language for program this project. The type of programming and the combination system schematic diagram circuit I explain briefly in the methodology section.

Work to be Completed by May 2, 2013
Next, I need to finish all the chapter of final report on formation by making corrections and proofing the chapter. This will be completed by May 2, 2013. I will continue the chapter until the end of chapter with does the hardware of this project. Every work I do will write on the report. I will then write the conclusion and management implications for the final paper. The entire project should be completed by the first week of May 2013.

Problems Encountered
During the research of my project Solar Power Tracker for Water Pumping System, I have some problems with the situation as the example did the output power after using my tracker devices is more than using the fixed solar panel. I have to do some calculation and research to encountered the problem. However the project is still on schedule and will proceed as how the project was planned.

Conclusion
My research project is on schedule and I should encounter no problems finishing it by May 2, 2013. If you have any questions or concerns with this project, please feel free to email me at fadhilsmile00@gmail.com